Kansas State University Bill Snyder Family Stadium

   Phase 2 Expansion KSU

Please click on images below for larger view.

Scope of Work

  • Procure
  • Expedite
  • Deliver
  • Warehouse
  • Install
  • Wrap Up

FF&E Management Services Provided

  • FF&E Package Value $2,016,963
  • Opened August 30, 2013, Gary Arthur Project Manager
  • FMSG procured, expedited, warehoused, delivered and installed the FF&E package for the KSU project.
  • FMSG provided Project Management, Coordination and Labor
  • FF&E package included suite and lounge furnishings, window treatment, multi-purpose room furniture and dining furniture
  • FMSG adjusted the delivery schedule to coincide with the construction schedule to ensure an on time completion.
  • FMSG conducted the punch list walk through process and took care of the few items in a timely manner.

Client Feedback

“I would like to thank you for all your help and hard work in making this project a success.  This was a very challenging project with many opportunities for failure.  In the end we worked together, to not only get the job done, but to go above and beyond to establish a very satisfied customer.  We couldn’t have done it without you.  I hope to have the opportunity to work with you again."

- Aaron Schneider
Field Engineer, Mortenson Construction

View full case study PDF

 