Scope

  • Project Management
  • Delivery and Coordination
  • Furniture & Equipment Installation

Project Details

  • Contacted in March 2005 to join the team building the new baseball stadium for the St. Louis Cardinals
  • Provided management, coordination, and labor for the delivery and installation of the FF&E package valued at $1.9 million
  • Supplied resources and contacts to furnish the stadium with all furniture, weight equipment, laundry, televisions, refrigerators, large trash containers, specialty items, etc.
  • Worked directly with the furniture and equipment manufacturers to schedule deliveries as the construction schedule permitted
  • Provided secured warehouse storage for product awaiting installation
  • Enlisted a Project Manager from within FMSG, Gary Arthur, who watched the schedule closely and responded to site requirements as needed to ensure timely delivery and installation
  • Followed the budget, pay application, change order, and punch list processes, enabling him to be the first contractor on the project to clear the items on his punch list

Client Feedback

"Hunt engaged in a very exhaustive competitive process to award this scope to a firm with demonstrated ability to be responsible to the needs of the Cardinals Ownership the project and delivery of product/installation in strict accordance with plans and specifications .... The superior performance of FMSG directly contributed to our ability to meet substantial completion deadlines. I would highly recommend this team for any project that requires such demand for predictable delivery."

- Marvin L. Johnson
Senior Project Manager